Heze Fuhai Energy's 20MW steam turbine generator set successfully completed the annual maintenance work and successfully started the machine in one go.
At 11:38 pm on June 22, 2019, our company fully invested and implemented the comprehensive technical transformation and efficiency improvement project of the 20MW steam turbine generator set flow structure under the contract energy management model, successfully completed the annual maintenance work, and successfully started the machine at one time and connected to the grid to generate electricity. All kinds of indicators of the unit were normal and the energy-saving effect was significant.
On July 18, 2018, our company completed the technical transformation and efficiency improvement and implemented the power supply. The energy saving and efficiency improvement ratio reached 11.32%, and the energy saving and efficiency improvement power reached 2000kw/h. Both the energy saving and economic benefits and social benefits were significant. During the five-year contract benefit sharing period, our company will be responsible for the maintenance, maintenance and maintenance of the unit free of charge.
According to Fuhai’s requirements, Fuhai Company is scheduled to start large-scale system shutdowns on May 31, 2019, implement annual routine maintenance of the entire factory, and plans to resume production on June 22, 2019. Our company attached great importance to it. On May 31, the company's deputy general manager Li Qingfeng led a team to the site to carry out maintenance coordination work, and organized the maintenance of the turbine unit body structure and control system, auxiliary machine inspection, condenser cleaning, vacuum system maintenance, and comprehensive generator inspection.
During the maintenance work, our company staff and supporting personnel from all parties overcome specific factors such as short construction period and heavy tasks. Under the full supervision of the DuPont expert group authorized by Fuhai, the professional third-party supervision unit, completed the maintenance task on time and with quality, and successfully started the machine and connected to the grid to produce electricity.
The annual maintenance work of the steam turbine unit was successfully completed, and it was unanimously praised by the owner Fang Fuhai Company and the professional supervision unit. It reflects the comprehensive and in-process supporting service level of our company's contract energy management project, demonstrates the company's business integrity, and demonstrates the excellent corporate style.
Here, the company extends high respect and sincere thanks to all the technical management personnel involved in the maintenance process, including the owners, third-party supervision units, outsourcing service providers, etc.!