Warm congratulations to Shanxi Fenyang Coking 12MW turbine flow transformation and energy-saving and efficiency improvement project for successfully passing the project acceptance
On October 13, 2021, our company's technical service project - Shanxi Fenyang Coking 12MW steam turbine unit circulation transformation energy-saving and efficiency improvement project successfully passed the project acceptance, with the energy-saving and efficiency improvement ratio reaching 13.79%, far exceeding the 10% assessment indicator agreed in the contract. I would like to express my warm congratulations here.
This project is to implement energy-saving technical transformation and efficiency improvement in the flow structure of the original unit. By increasing the pressure level, optimizing the blade line, configuring the cylinder structure and other technical means, the main body's functional power can be increased, so that the unit can produce more force, more work, and more electricity under the same working conditions, thereby directly generating economic benefits.
On October 9, 2021, after 168 hours of aging operation, the two parties conducted on-site actual measurement and comparison, and calculated that under the same working conditions, the energy-saving efficiency improvement ratio after the transformation was 13.79%, that is, under the same working conditions, the energy-saving power can be generated at 1379kw/h. According to this calculation, the annual direct energy-saving income of the project reached more than 4.4 million yuan, and the economic and social benefits of the project were very significant.
Customer acceptance evaluation of this project is "all parameters are within the required scope and are running well; continuous full load operation is stable, vibration does not exceed 2 wires, thermal swelling returns to normal state, the efficiency increase ratio exceeds 10% of the expected, reaching 13.79%. The completion acceptance is agreed, and the quality acceptance is subject to completion after the warranty period is over; after trial operation, the efficiency improvement is benchmarked, and the contract agreement is in compliance with the acceptance."
At the same time, the customer highly praised our company's comprehensive management service level for project construction and highly praised our company's excellent style of being brave in innovation and daring to face tough work during the project construction process. Here, our company sincerely expresses its highest respect and sincere thanks to all the colleagues responsible for energy use units, brother units from outside the project!
With the continuous deepening of the national strategy of "carbon peak and carbon neutrality", combined with the continuous rise in coal, energy and industrial electricity prices, energy-saving and technical transformation work such as comprehensive utilization of waste heat and waste pressure resources, and the efficiency improvement of industrial electromechanical equipment transformation has become an urgent task. Energy conservation and environmental protection, technical transformation and efficiency improvement have become a necessity for improving the competitiveness of enterprises and survival and development. Potential energy-consuming units are welcome to visit and exchange for common development and win-win cooperation!