- Party Group of the Shandong Energy Supervision Office of the Communist Party of China: Deeply promote the integrated construction of Shandong's power market
- State Power Investment Group holds a regular meeting on production and operation in March
- Focus | Electric Power Redemption and Transcendence on the Eve of Great Changes
- Preview of the Two Sessions | Use the power of the market to support energy transformation
Industry News
Summary of weekly power projects (2023.8.7-8.11)—Approval, start of construction, grid connection, etc.
Polaris Power Network compiled the week from August 7, 2023 to August 11, 2023Electricity Projects: It involves approval, start-up, grid connection for thermal power, hydropower, wind power, nuclear power, power transmission and distribution, and energy storage projects.
Big project! Golmud coal-electricity integration project successfully passed the feasibility study review
From August 2 to 4, the feasibility study and evaluation meeting of the Golmud coal-electricity integration project was held in Beijing. The feasibility study report of this project is feasible and the project has passed the feasibility study review. The project construction site is located in Golmud City, Haixi Prefecture, Qinghai Province, with a scale of 2×660,000 kilowatt coal-electricity unit.
2×1 million kilowatts! The feasibility study report of Shaanxi Coal and Miluo Thermal Power Project passed the review
On August 9, the review meeting of the feasibility study report of Shaanxi Coal Miluo 2×1 million kilowatt coal-fired power generation project closed in Changsha City. The meeting passed the project feasibility study report, marking the project entering a substantive stage.
Guoxin Jingjiang 2×1 million kilowatt unit expansion project officially started
On the morning of August 8, the unveiling ceremony of Jiangsu Guoxin Mazhou Power Generation Co., Ltd. and China Coal Jingjiang Power Generation Co., Ltd. and the launching ceremony of the Guoxin Jingjiang 2×1 million kilowatt unit expansion project were grandly held in Jingjiang City. This project is Guosen Group's first central-local coal-fired power joint venture cooperation project, building two 1 million kilowatt ultra-supercritical secondary reheating and efficient clean coal-fired generator sets and related auxiliary facilities. According to feasibility study estimates, the annual power generation of the project is about 10 billion kilowatt-hours, with an average annual tax of 200 million yuan.
The President attended! Units 7 and 8 of the Wangji Power Station Expansion Project of Zimbabwe are put into production and power generation
On August 3 local time, Zimbabwe President Emerson Mnangagwa attended the launch of power generation for Units 7 and 8 of the Zimbabwe Wangji Power Station expansion project. This project is a flagship project supported by the Chinese government under the framework of the "Belt and Road" and is the largest infrastructure project since Tianjin's independence. The annual power generation of the two new units will exceed 4 billion kilowatt-hours, and their full production will increase the installed capacity of the Wangji Power Station from the current 920 MW to 1,590 MW.
The first gas generator stator of the second phase of Zhaoqing Power Plant of the State Energy Group was successfully lifted and put into place
On August 4, the first gas generator stator of the second phase of the Zhaoqing Power Plant of the State Energy Group Guangdong Company was hoisted and put into place, marking the full launch of the installation of the main equipment of the gas generator set. The successful lifting of the stator of Unit 3 is one of the important milestone nodes in the construction of the second phase of the project, marking the installation stage of the company's second phase of the gas project, such as gas turbines, steam turbines, generators, waste heat boilers, etc., and lays a solid foundation for the unit to start production and generate power on schedule.
The construction project of Guoneng Huizhou Thermal Power Outside Supply Compressed Air Station has started!
On August 8, the construction ceremony of Guoneng Huizhou Thermal Power Outside Supply Compressed Air Station Construction Project was held, and the project entered the engineering construction stage in full swing. The project is located in Daya Bay Petrochemical District, Huizhou City, Guangdong Province. It is planned to build three new external compressed air stations and waste heat recovery systems with a minimum supply of 650 cubic meters per minute. After completion and production, it is expected to provide 84,480 cubic meters of compressed air every year and recover 9.6 million kcal of waste heat per hour.
1600MW! Construction of the gas turbine power plant project in Abuja, Nigeria
On August 4, local time, the Abuja Gas Engine Power Station project started. The power station is one of the terminal supporting projects for gas supply of Ajokuta-Kaduna-Kano (AKK) natural gas pipelines with national strategic significance. The overall planned total installed capacity of the project is about 1,600MW. The project started this time is a phase one project with a planned installed capacity of 350MW and a construction period of 36 months.
China Energy Construction signed a survey and design contract for 590 MW combined cycle power plant project in Anwara, Bangladesh
Recently, China Energy Construction Northeast Institute and Harbin Electric International Engineering Co., Ltd. signed a survey and design contract for the 590 MW combined cycle power plant project in Anwara, Bangladesh. The project is located in Anwara, Chittagong, Bangladesh. It is the first survey and design project of the Northeast Institute to adopt Siemens 8000H-class gas engine under the "Belt and Road" initiative. The net installation output is 590 megawatts, and the site has reserved conditions for the second phase of expansion.
2×660MW! Unit 2 of the Huadian Indonesia Boya Project was successfully connected to the grid for the first time
At 12:40 local time on August 8, Indonesian time, Unit 2 of the Boya Indonesia 2×660MW project was successfully connected to the grid for the first time. This is another important milestone node in the construction of the project after Unit 1 is connected to the grid with load trial operation. Huadian Indonesia Boya 2×660MW Kengkou Power Station is an important landmark project along the "Belt and Road". The two units were connected to the grid on July 20 and August 8.
Hydropower Projects
The feasibility study report of the world's largest hybrid pumped energy storage project has passed the review!
Recently, the feasibility study report of mixed pumped storage power stations in the two estuary of Yalong River in Sichuan passed the review. The power station is the world's largest hybrid pumped storage project, located in Yajiang County, Ganzi Prefecture, Sichuan Province, with an installed capacity of 1.2 million kilowatts. Together with the built Lianghekou Hydropower Station installed 3 million kilowatts as a conventional unit, the total installed capacity is 4.2 million kilowatts.
1200MW! The review meeting on the report on the "three special topics" of the feasibility study of pumped storage power station in Ruyang, Henan was held
From July 30 to 31, a review meeting was held in Changchun City for the special report on the research on the feasibility study stage of the Ruyang pumped storage power station in Henan Province, a special report on the selection of normal water storage levels and a special report on the general construction layout planning. The power station is located in Ruyang County, Luoyang City, Henan Province. It has an installed capacity of 1,200MW, a rated head of 417m, and a distance height ratio of 8.64.
Nanwang Energy Storage Signs a tripartite agreement on the construction of pumped energy storage projects
On August 9, 2023, China Southern Power Grid Energy Storage Co., Ltd. jointly signed the "Framework Agreement on Cooperation to Promote the Development and Construction of Kunming Yiliang Pumped Storage Power Station Project" with the People's Government of Yiliang County, Kunming City, Yunnan Province and China Railway Construction Development Group Co., Ltd. The Yiliang Pumping Energy Storage Project is located in Goujie Town, Yiliang County, Kunming City, with an initial planned installation capacity of 1.2 million kilowatts. In order to accelerate the implementation of the Yiliang pumped energy storage project, the three parties reached a agreement based on the principle of equality and mutual benefit.
The world's first! The central body forging of the rotor of the maximum single-machine capacity of 500MW class impact turbine unit has been successfully developed
On August 7, the world's first single-unit 500MW class impact turbine rotor center body forging developed by the State Machinery Reinstallation was successfully shipped and delivered to Oriental Electric Group Oriental Motor Co., Ltd. The forging will be used in Datang Zala Power Station in China. The forging has zero defects in flaw detection, and all inspection indicators fully meet the technical requirements, marking that the double equipment has mastered the key technologies in the entire process of manufacturing forgings of 500MW class impact wheel center body, and achieved a breakthrough in the "from 0 to 1" of 500MW class martensitic stainless steel impact wheel forgings.
1200MW! The design plan for the main civil construction standards of Anhui Shitai Pumped Storage Power Station passed the review
From August 7 to 10, an review meeting on the construction organization design of the main civil construction standards of Anhui Shitai Pumped Storage Power Station was held in Chizhou City. The meeting believed that the content and depth of the civil engineering standard construction organization design plan of Shitai extraction and storage main project meet the relevant regulations and specification requirements, and agreed that the plan will pass the review.